VIDEO. How Carnon beach finds sand between the groynes

VIDEO. How Carnon beach finds sand between the groynes

Des travaux réalisés par l'entreprise occitane de BTP Cazal. PCa

Depuis mardi 27 février, une drague danoise prélève le sable à la sortie du port de La Grande-Motte pour renforcer le cordon dunaire à l’intérieur des trois épis nouvellement créés à Carnon.

Also read: Near Montpellier, a Danish dredger to resilt Petit Travers beach

The "Magni", a 75 m vessel from the Danish group Rohde Nielsen specializing in dredging and coastal protection, began its rotations on Wednesday evening.

"Our team works in three shifts, 24 hours a day, explains Maxime Bel, the site manager of the construction site ;#39;occitan construction company Cazal, in charge of work on land. And there we are for ten days non-stop!"

Ultimately, the operation will gain at least 40 meters of beach, or even more in places.

Add a Comment

Your email address will not be published. Required fields are marked *

(function(d,s){d.getElementById("licnt2061").src= "https://counter.yadro.ru/hit?t44.6;r"+escape(d.referrer)+ ((typeof(s)=="undefined")?"":";s"+s.width+"*"+s.height+"*"+ (s.colorDepth?s.colorDepth:s.pixelDepth))+";u"+escape(d.URL)+ ";h"+escape(d.title.substring(0,150))+";"+Math.random()}) (document,screen)